Project Overview

New build office fit-out.

Project Description

The new client for this building wanted to incorporate hot desk working to their business. To achieve this underfloor power track systems were designed and wired to suit the office plan layouts.

Project Works Detail

  • Mains & sub mains
  • Main & secondary containment
  • Installation of small power via under-floor track system for floor outlet boxes, desk power modules and general purpose power to serve the office areas
  • Comms room supplies and UPS
  • Power poles
  • Mechanical supplies
  • Lighting and emergency lighting designed and installed throughout
  • Fit-out of the landlord core areas throughout the building (staircases and toilets)
  • Disabled alarm systems
  • Testing and commissioning